Estimating Of Steel Bar Quantity for Construction
Planning quantity for steel bars in each development is an arduous work. It needs a talented and experienced quantity assessor, estimators or engineers to make one. Each area, sub-segment, and parts of the plans with fortifying bars ought to be incorporated as missing one would be exorbitant and ruinous over the long haul.
Mat Foundation
The accompanying should help engineers on focuses to consider in deciding the strengthening bar quantity for Matt foundation.
Learn More
The following is an example count for mat foundation rebar quantity.
Given
Business length per fortifying bars = 12 l.m. , (to be deducted with splicing length @ 0.8m)
Top bars
Transverse quantity = W/s= 100/0,3=333.3,say 334 pcs100 l.m.
100 + t + t = 100 + 1 + 1 = 102 l.m., 334 pcs (Additional length for hooks)
334 X 102 = 34,068 all out straight meter
(All out straight meter)/(business length-splicing)= 34,068/(12-0.8)=3,042 pcs-12meter length strengthening bars
Longitudinal quantity = L/s= 100/0,3=333.3,say 334 pcs100 l.m.
100 + t + t = 100 + 1 + 1 = 102 l.m., 334 pcs (Additional length for hooks)
334 X 102 = 34,068 all out direct meter
(All out direct meter)/(business length-splicing)= 34,068/(12-0.8)=3,042 pcs-12meter length strengthening bars
Total Quantity for TOP BARS
Transverse QTY + Longitudinal QTY = 3,042 + 3,042 = 6,084 pcs ? 12mL fortifying bars
Computing base bars is equivalent to the top bars.
Learn More
Columns
Here is a guide on deciding the quantity for strengthening bars for column.
Test computation for columns:
For more information, please visit PC Steel Bar.
Given
W = 0.4 m
L = 1.0 m
H = 3.0 m
Primary bar pcs. = 16
Absolute number of ties = 20 pcs.
Business length of strengthening bars = 8.0 l.m.
Primary bar
Strengthening Ties
Length per ties is the border, P = 2W + 2L = 2(0.4) + 2(1.0) = 2.8 m
Absolute length = Length x No. of ties = 2.8 x 20 = 56 straight meter
Absolute number of pieces = (Total length)/(Commercial length) 56/8=7 pieces-8 meter length rebars
Slab on Grade
The accompanying methodology will help engineers on deciding the quantity of strengthening bars in slab on grade.
Sample figurings are given below.
Temperature bars
L = 10.0 m
W = 10.0 m
t = 0.6 m
s = 0.25 m
Business length of strengthening bars = 12.0 l.m.
Transverse bars
(same figuring for longitudinal bars since this is a square SOG)
No. of pieces = W/s= 10/0.25= 40 pieces-12 straight meter
Complete number of pieces = Transverse + Longitudinal = 40 + 40 = 80 pcs ? 12 straight meter strengthening bars
Learn More
Suspended Slab
The accompanying aide should assist you with deciding the required strengthening bars for suspended slabs.
Other Post
Are you interested in learning more about PC Bar? Contact us today to secure an expert consultation!
Previous: Buying an Air Hose? Read This Blog First for 10 Expert Tips!
Next: Can You Install New Shingles Over an Existing Asphalt ...
If you are interested in sending in a Guest Blogger Submission,welcome to write for us!
All Comments ( 0 )